Poso Hospital Project Worth Rp265.7 Billion Starts: Piles from Makassar

波索医院项目2657亿盾开工:桩基材料从望加锡运来

Construction of an additional building for the Poso Regional General Hospital (RSUD Poso) in Central Sulawesi formally entered the execution stage in early November 2026. The Poso hospital project has a contract value of Rp265,738,789,679, is funded by the state budget under a 2026–2027 multi-year contract, and is being built by PT Citra Prasasti Konsulindo (Cipako) over 453 calendar days. When the site was checked on 7 November, stone, sand and chippings were already there, while piles and piling equipment were still on their way from Makassar. For suppliers it shows the Central Sulawesi supply pattern: local aggregates, manufactured materials from South Sulawesi.

Key Facts

Poso hospital project: value, contractor and schedule

According to Radar Sulteng reports carried by Kabar68 and Lintas Sulawesi News on 9 November 2026, the work is an additional building for RSUD Poso. It is funded by the state budget through a multi-year contract (MYC) covering the 2026–2027 budget years. The contract value is Rp265,738,789,679 and the contractor is PT Citra Prasasti Konsulindo, or Cipako.

The contract was signed on 1 October 2026 with an execution period of 453 calendar days. Counted from the contract date, the period ends around late December 2027. Local residents who were interviewed hope the new building can be used in about a year and a half.

The project leader, Endai Dasuki, said there had been no significant problems so far. The team was still preparing the main works while waiting for piling equipment and piles to arrive from Makassar. He also said the budget allocation was secured through coordination between the Central Sulawesi provincial government, the Poso regency government and the central government.

Material supply chain: local aggregates, factory products from South Sulawesi

A site visit in Maliwuko village, Lage district, on Saturday 7 November 2026 found stone, sand, chippings and supporting materials already in place. Manufactured materials and the main equipment, on the other hand, were still being mobilised from South Sulawesi to Poso.

This pattern is common for projects outside the big cities. Aggregates can come from nearby sources, while factory products such as concrete piles, reinforcing steel, bulk cement and building components have to be shipped from more distant distribution hubs. In Poso’s case, Makassar was named directly by the contractor as the origin of the materials.

For a hospital building, the pile foundation is usually the first major stage before the superstructure. The timely arrival of piles and piling rigs therefore decides whether the next works can start on schedule.

Opportunities and notes for building-material suppliers

For building shops and distributors in Central Sulawesi, a multi-year project like this creates material demand that lasts more than one budget year, from structural work to finishing. A few points to keep in mind:

  • Procurement usually follows the technical specification and the contract bill of quantities, so quality documents such as SNI marks and product certificates should be ready.
  • Shipping distances from South Sulawesi mean lead times and freight costs must be calculated from the start.
  • Cement and other moisture-sensitive materials need proper storage in the site warehouse.

homeX follows construction projects across Indonesia and can help contractors and suppliers prepare material lists, compare supply sources and plan deliveries to the project site.

Poso hospital project: related articles and products

FAQ

Who is building the Poso hospital project and what is it worth? The RSUD Poso additional building is being built by PT Citra Prasasti Konsulindo (Cipako) under a Rp265,738,789,679 contract funded by the state budget over 2026–2027.

How long will construction of RSUD Poso take? The execution period is 453 calendar days from the contract signing on 1 October 2026.

Where do the materials for the Poso hospital come from? Stone, sand and chippings are already on site, while factory-made materials and equipment are being mobilised from South Sulawesi; piles and piling rigs are coming from Makassar.

For building and renovation material needs, reach the homeX team on WhatsApp +62 821 1818 998, by email at homex9998@gmail.com or through our contact page.

Sources: Kabar68/Radar Sulteng: Rp265 billion Poso hospital project begins (9 Nov 2026); Lintas Sulawesi News: Rp265 billion for RSUD Poso (9 Nov 2026)