Concrete Curing for 7 Days and Formwork Removal at 30 Hours: Bina Marga Guide

混凝土养护 7 天与拆模 30 小时:Bina Marga 施工指南要点

Concrete curing means keeping concrete moist and at a fairly constant temperature so the cement hydrates fully. The Guide for Concrete Works on Roads and Bridges, Pd T-07-2005-B from the Directorate General of Highways (Bina Marga), Ministry of Public Works, gives clear figures: wet covering for at least 7 days, formwork on thin walls and columns not removed before 30 hours, and formwork under slabs and beams waiting for a compressive test of 85% of design strength. This article summarises clauses 4.6, 6.3, 7.3, 8.1, 8.4, 9.1 and 9.2 plus Tables 5 and 6. The guide is for roads and bridges, not houses; for a house the figures can serve as a benchmark, and the final decision rests with the structural designer. Data as of 23 October 2026.

Concrete curing, formwork removal and slump: figures from Pd T-07-2005-B

StageWhat the guide saysClausehomeX noteSource
Weather when pouringPouring must be shielded from direct sun; it must not be done when the evaporation rate exceeds 1.0 kg/m²/hour (ACI 305.R-77 chart), nor during rain or in dusty air; the pour location is kept free of rain with a tent4.6 and 7.1We did not copy the evaporation chart; the guide only gives the 1.0 kg/m²/hour limitKementerian PU (Bina Marga)
PouringWritten notice at least 24 hours before the pour; pouring into the formwork finished within 1 hour of mixing (unless a retarder is used); layers of at most 15 cm for complex shapes or dense reinforcement, up to 30 cm for walls; free-fall height at most 150 cm; no water may flow over the surface in the first 24 hours; old concrete faces are roughened and treated with a tested bonding agent7.3For ready-mix deliveries, the 1-hour limit has to be compared with the travel time and pump scheduleKementerian PU (Bina Marga)
Planned slump (Table 5)Walls, foundation slabs and reinforced footings 5.0–12.5; unreinforced footings, caissons and underground works 2.5–9.0; slabs, beams, columns and walls 7.5–15.0; road pavement 5.0–7.5; mass concrete 2.5–7.5; measured slump must not exceed the planned slump by more than 20 mm6.3 (Table 5) and 9.1Data gap: Table 5 in the PDF copy we read does not print a unit; since the tolerance is written as 20 mm, the unit is probably cm (homeX inference, not data)Kementerian PU (Bina Marga)
Wet curingProtect the concrete from early drying, excessive heat and mechanical disturbance; start as soon as the concrete begins to harden (before plastic shrinkage cracks) by covering it with water-absorbent material kept saturated for at least 7 days and in contact with the surface; timber formwork not yet removed is kept wet8.4 a, b7 days is the minimum in this guide, not a quality guarantee; no specific material such as burlap is namedKementerian PU (Bina Marga)
Special casesA concrete surface used directly as a wearing course is cured with a 5 cm layer of damp sand for at least 21 days; high early-strength cement concrete is kept wet until it reaches at least 70% of the 28-day design strength8.4 c, dApplies to wearing surfaces (e.g. a carport floor without tile cover) and high early-strength cement; the guide does not mention PCC or OPCKementerian PU (Bina Marga)
Formwork removalVertical faces, walls, thin columns and similar must not be stripped earlier than 30 hours after pouring, without neglecting curing; formwork supported by props under slabs, beams, girders or arches must not be removed until a compressive test shows at least 85% of design strength or a calculation shows the load can be carried; exposed surfaces for finishing are stripped 9 to 30 hours after pouring8.1The 30-hour and 85% figures come from a road and bridge guide; for a house, agree them with the structural designer and test specimen resultsKementerian PU (Bina Marga)
7- and 28-day compressive tests (Table 6)One pair of specimens for each mix poured, at least one set per grade and per component type cast separately each day; cylinder 15–30 cm minimums: fc 15 MPa 9.5 (7 days) and 14.5 (28 days); fc 20 15.0 and 21.0; fc 25 18.0 and 25.0; fc 30 21.0 and 29.0; fc 35 24.0 and 33.0 MPa; if the 7-day result is below the requirement, pouring stops until the cause is known9.2 and 6.3 (Table 6)Table 6 is the same one discussed in our K-to-fc concrete grade conversion article; here it is used only for the 7-day test limitsKementerian PU (Bina Marga)

Source: Pd T-07-2005-B, Guide for Concrete Works on Roads and Bridges, Directorate General of Highways (Bina Marga), Ministry of Public Works (clauses 4.6, 6.3, 7.3, 8.1, 8.4, 9.1, 9.2; Tables 5 and 6). Data gaps: this document is for roads and bridges, not houses; the Table 5 unit is not printed in the copy we read; we did not read SNI 2847 or other concrete SNIs, so no house-specific figures are set; the steam curing clause (8.5) is not covered; no Indonesian weather or temperature data were checked. The document code carries 2005; we did not check whether a newer revision exists. Not engineering advice; consult a structural designer. Data as of 23 October 2026.

How to read the concrete curing figures for a house (homeX analysis)

homeX analysis, not guide data: the guide sets minimums for supervised road and bridge works. For a house slab or beam pour, three things are easiest to check and consistent with the guide: (1) record the mixing time and the finish time of the pour; (2) start covering and wetting as soon as the surface hardens and keep it saturated for at least 7 days; (3) do not remove props under a slab or beam without the designer approval, because the guide requires proof of 85% strength or a calculation. When exactly a slab may be loaded is not set here.

Buyer tips

  • Record the mixing time and the finish time; the 1-hour limit in the guide counts from mixing.
  • Start wet covering as soon as the surface hardens and keep it saturated for at least 7 days.
  • Do not remove props under slabs or beams before the designer approves.
  • Make specimens for each grade and pour day; a low 7-day result is a signal to stop and check.

Request a concrete curing quote for your project

homeX can compare several brands at once and prepare a written quote for projects, renovations or shop stock. Send your needs (brand, size, quantity, location) via WhatsApp +62 821 1818 998, or visit the homeX showroom: Priskilla Tower, 6th floor, Jl. Atang Sanjaya No.21, Benda, Kota Tangerang, Banten 15125. Visit the homeX Showroom.

Disclaimer: prices change without notice and differ by store, city, pack size, grade and promotion. Data as of 23 October 2026; always confirm with the seller before buying.

FAQ

How long is concrete curing per the Bina Marga guide? Clause 8.4 asks for water-absorbent material kept saturated for at least 7 days. A concrete wearing course uses 5 cm of damp sand for at least 21 days, and high early-strength cement concrete is kept wet to 70% of the 28-day strength.

When can formwork be removed? Per clause 8.1, vertical faces, walls and thin columns are not stripped before 30 hours; formwork under slabs or beams waits for a compressive test of at least 85% of design strength or a load calculation.

Does this guide apply to a house slab pour? Not directly: Pd T-07-2005-B is for roads and bridges. Its figures can be a benchmark, but for a house the decision follows the structural designer and building standards we have not read.

Concrete curing: related articles and products

Related articles:

Related products at homeX:

Price sources (checked 23 October 2026): Kementerian PU (Bina Marga) — Pd T-07-2005-B: Concrete works for roads and bridges (clauses 4.6, 6.3, 7.3, 8.1, 8.4, 9.2, Tables 5 and 6).

Ask for a Price on WhatsApp +62 821 1818 998